- 고객 사례 예 2017/11/28 UP
-
HEADLINE
・Understanding and analysis of machine stops without human intervention. Future tasks became apparent.
・Data sharing between management and factory workers. A united commitment to improvement.
Identified troubles on the shopfloor without human intervention.
Analysis of causes of machine stops made challenges and their proprieties apparent.

So far, it was difficult for managers to figure out which machine stopped its operation, when and how long. President Masahiro Akitani laughingly recalls: “For example, we came to the factory in the morning and found a machine stop, but we could not know when the machine stopped. Also, the factory staff does not want to report “bad news” to managers This makes it difficult to fully understand the actual situation on the shopfloor.”
DMG MORI Messenger made a huge step towards visualizing the situation inside the factory without investing additional human resources. It visualized the type, timing and extent of the troubles and problems to be solved. Furthermore, 6 months after introducing DMG MORI Messenger, the company could identify causes of machine stops. and A cycle of steady improvement started running.

“Looking at the results, about half of the machine stops were handling time and other processes, leaving little room for improvement. However, most of the remaining half of machine stops occurred due to chips blocking the tool measuring sensor or chip deposition close to the workpiece seating or door opening. We could solve these problems by improving the operation. We also realized that machine stops due to mechanical trouble were very limited.” Based on these results, the company gave priorities to the measures to carry out.
By attending to each one of their problems, the availability of their machines improved from 60% at introduction of DMG MORI Messenger to the current level as high as 80%.
President Akitani admits that he assumed the availability to be higher than 60% before introducing automation, although he didn’t know the precise situation inside the factory. His wrong assumption shows the importance of clear visualization to achieve productivity improvement.
Shared visualized data by everyone involved.
Strengthened commitment for improvement together by management and factory workers.
The information gained from DMG MORI Messenger is viewed not only by the management, but also passed back to the factory staff as feedback. Now, the factory staff is slowly changing their attitude and started to proactively report problem solutions to the management. It is thanks to making data visible, that the staff on every level of the company shares the same awareness and commitment towards improvement. (Continued in Part 3)
This content is for members only